天天彩票

  • <tr id='Aaezkf'><strong id='Aaezkf'></strong><small id='Aaezkf'></small><button id='Aaezkf'></button><li id='Aaezkf'><noscript id='Aaezkf'><big id='Aaezkf'></big><dt id='Aaezkf'></dt></noscript></li></tr><ol id='Aaezkf'><option id='Aaezkf'><table id='Aaezkf'><blockquote id='Aaezkf'><tbody id='Aaezkf'></tbody></blockquote></table></option></ol><u id='Aaezkf'></u><kbd id='Aaezkf'><kbd id='Aaezkf'></kbd></kbd>

    <code id='Aaezkf'><strong id='Aaezkf'></strong></code>

    <fieldset id='Aaezkf'></fieldset>
          <span id='Aaezkf'></span>

              <ins id='Aaezkf'></ins>
              <acronym id='Aaezkf'><em id='Aaezkf'></em><td id='Aaezkf'><div id='Aaezkf'></div></td></acronym><address id='Aaezkf'><big id='Aaezkf'><big id='Aaezkf'></big><legend id='Aaezkf'></legend></big></address>

              <i id='Aaezkf'><div id='Aaezkf'><ins id='Aaezkf'></ins></div></i>
              <i id='Aaezkf'></i>
            1. <dl id='Aaezkf'></dl>
              1. 您的位置: 首页 >新闻中心 >基层动态

                务川项目#1机组锅炉点火吹管圆满完成

                发表于:2019.03.3011:18 作者: 禾乔

                  3月29日上午10时36分,公司EPC总承包贵州务正道1000kt/a氧化铝热电站工程,#1锅炉点火吹管重要里程碑进度计划工作圆满完成。 

                  #1锅炉点火吹管,是继3月10日完成锅炉酸洗后,如期完成的又一项重要里程碑节点。3月21日8时58分,#1锅炉点火一次成功后,完成了锅炉高温烘炉及吹管工作。工程公司科学研究院调试人员,精细策划,精心调试,助推了本节点的顺利完成。本次吹管采用降压吹管的方式,共分三个阶段进行吹扫,有效吹扫117次,其中第116、117次连续两次打靶,斑痕不大于0.5mm,且0.2-0.5mm斑痕少于5点,优于验收标准。 

                  在各参建单位专家领导的共同见证下,确认吹管合格。为下一阶段汽轮机冲转及整套启动、以及氧化铝投料试车打下了坚实的基础。